Giti brings premium tires, in
Sep 10, 2023The Best Duffel Bags of 2023
Sep 29, 2023Tech Talk: Local rocketeer dreams of taking out the trash
Nov 11, 20232022 Ford Maverick Lariat FWD review
Sep 06, 2023You Can Make Your Home A Hell Of A Lot Nicer With Any Of These 40 Genius, Cheap Things On Amazon
May 21, 2023Report 11/2022: Collision between a passenger train and a hand trolley at Challow
Collision between a passenger train and a hand trolley at Challow, Oxfordshire, 21 October 2021.
R112022_221013_Challow
At 06:09 hrs on 21 October 2021, a passenger train travelling at 123 mph (198 km/h) struck a hand trolley on the track near Challow, Oxfordshire. The train was the first to pass through the area after the completion of overnight maintenance work. There were no injuries among the passengers or crew on board and the train did not derail. The hand trolley was destroyed by the impact and debris from it caused damage to equipment under the train. The collision also resulted in minor damage to the track.
A maintenance team had carried out overnight work at Challow and no one noticed the team had left its hand trolley on the track. The checks undertaken before handing back the railway for normal operation also had not identified the hand trolley's presence. A process which formed part of these checks was the line clear verification process. It was used to monitor what vehicles, including hand trolleys, were placed on and taken off the track during the overnight work. However, there were weaknesses within this process, and these were compounded by the maintenance team not following the process as it was required to on the night concerned.
Underlying factors related to the weaknesses within the line clear verification process were:
A further probable underlying factor was that hand trolleys were being routinely used at night without displaying any red lights and that no assurance activities were taking place within work sites to monitor compliance to this requirement.
RAIB observed that after the accident, the train was allowed to travel at a speed above that which should have been permitted given the level of damage it had sustained. RAIB also observed that there were multiple issues with how the work at Challow was planned by Network Rail.
RAIB has made five recommendations to Network Rail. The first is to establish how the existing line clear verification process can be improved while the second is to consider what technology could be used by its staff to support the process. The third recommendation is to propose an amendment to the Rule Book so that hand trolleys are required to display an illuminated red light in both directions at all times when on the track. The fourth is for Network Rail to have processes in place to ensure that any hand trolley placed on its track has illuminated red lights displayed in both directions. The fifth recommendation is to review the effectiveness of its safety assurance activities which check that hand trolleys are being used correctly and safely.
RAIB also identified three learning points. The first reminds maintenance staff about the importance of complying with all rules and standards concerning how trolleys and rail skates should be used on Network Rail's infrastructure. The second highlights the importance of clear communication between the staff at a train involved in an accident and those based in control rooms to establish what damage has been sustained by a train, so that the appropriate controls can be put in place before the train is permitted to move. The third is that staff involved in planning maintenance work produce documents that are accurate, appropriate and specific for the task that is being carried out, and involve those responsible for the work in the planning of it.
Response to recommendations:
RAIB Recommendation response for Challow